Performance Evaluation of Woven Polyethylene Formwork on Tie Beam and Pile Cap Structure in Terms of Cost and Time
Novena Ulimandalany Barus , Jessica Sjah *, Ayomi Dita Rarasati
Department of Civil Engineering, Faculty of Engineering, Universitas Indonesia, Depok, West Java, Indonesia
ABSTRACT
One of the most important components in the construction execution is concrete works. Therefore, we need formworks to form the structural elements that are planned in a construction process. In the process, an economical alternative needs to be taken regarding choosing formwork material to get more benefits, both in terms of cost and time. Fabric formwork can be an alternative solution for formwork material. An example of a feasible formwork material alternative is woven polyethylene-based formwork. The purpose of this research is to evaluate the performance value of woven polyethylene formwork and compare it with the conventional formworks such as wood and brick in terms of cost and time. Field observations and literature reviews have been done to answer these questions. By using woven polyethylene formwork on tie beam and pile cap structure, it was found that the average time and the investment cost of installation are consecutively 344.23 s/m2 and IDR75000 which is faster and cheaper than using conventional ones.
KEYWORDS
Fabric Formwork, Woven Polyethylene, Concrete Structure, Construction, Performance Evaluation
Cite This Paper in IEEE or APA Citation Styles
(a). IEEE Format:
[1] Novena Ulimandalany Barus , Jessica Sjah , Ayomi Dita Rarasati , "Performance Evaluation of Woven Polyethylene Formwork on Tie Beam and Pile Cap Structure in Terms of Cost and Time," Civil Engineering and Architecture, Vol. 8, No. 3, pp. 305 - 311, 2020. DOI: 10.13189/cea.2020.080314.
(b). APA Format:
Novena Ulimandalany Barus , Jessica Sjah , Ayomi Dita Rarasati (2020). Performance Evaluation of Woven Polyethylene Formwork on Tie Beam and Pile Cap Structure in Terms of Cost and Time. Civil Engineering and Architecture, 8(3), 305 - 311. DOI: 10.13189/cea.2020.080314.