Analysis of Control of Costs and Time with Earned Value Method on Road Maintenance Projects in Palmerah District, West Jakarta
Sandy Radhitya Akbar *, Asep Setiawan , M. Rozahi Istambul , Raden Herdian Bayu Ash Siddiq
Department of Civil Engineering, Faculty of Engineering, Widyatama University, Bandung, East Java, Indonesia
ABSTRACT
Control in a construction project generally involves three main aspects, namely: cost, time and human resources. This study uses Network Planning analysis as a control function with the Critical Path Method (CPM) method in calculating the difference in cost and time needed to complete the work with a planned budget and schedule. This study also tried to implement an integrated control function, namely the Earned Value Method for a construction project. Based on the analysis and calculation in the 8th week (eight) of the total duration of the project, the analysis produces CPI value = 1.06 which shows that the performance of contractor's expenditure costs is more efficient than the planned budget. The description of the final condition of the project also shows that there is a residual budget value of Rp 321,642,608.01 or 5.55% of the total value of the overall project cost budget or Budgeted At Completion (BAC) which is an advantage for the contractor. The analysis also produces SPI value = 0.94 which means that the time performance index is of good value but the execution of the work is a little slower than the overall planned schedule.
KEYWORDS
Critical Path Method, Earned Value Method, Metode Nilai Hasil, ACWP, BCWP, BCWS, BAC, CPM
Cite This Paper in IEEE or APA Citation Styles
(a). IEEE Format:
[1] Sandy Radhitya Akbar , Asep Setiawan , M. Rozahi Istambul , Raden Herdian Bayu Ash Siddiq , "Analysis of Control of Costs and Time with Earned Value Method on Road Maintenance Projects in Palmerah District, West Jakarta," Civil Engineering and Architecture, Vol. 7, No. 3A, pp. 27 - 34, 2019. DOI: 10.13189/cea.2019.071305.
(b). APA Format:
Sandy Radhitya Akbar , Asep Setiawan , M. Rozahi Istambul , Raden Herdian Bayu Ash Siddiq (2019). Analysis of Control of Costs and Time with Earned Value Method on Road Maintenance Projects in Palmerah District, West Jakarta. Civil Engineering and Architecture, 7(3A), 27 - 34. DOI: 10.13189/cea.2019.071305.